Client: SEKAF Company
Waterproofing Contractor: Mana Sanat Bonyan
Objective: waterproofing of excavation
Case of Activity: Consulting, Technical Designing, Procurement and Installation of Waterproofing System
Groundwater Level: -12 m
Excavation Floor Area: 5000 m²
Excavation Wall Area: 6000 m²
Excavation Depth: 23 m
Stabilization System: Nailing and Soldier Pile
Designing and Installation of Waterproofing System:
- Installation of Dimple Sheet Drainage Layer on vertical surfaces
- Installation of GCL Waterproofing Layer
- Using Sodium Bentonite Powder in overlap areas
- Installation of LLDPE Waterproofing Layer
- Installation of Geotextile Protective Layer